Project Name : İCDAS Biga Iron-Steel Factory
Construction
Project Location : Biga
Starting Date : Jan 2007
Completion Date : Still going on...
Number of operating cranes : 16
1-Liebherr LR 1250 (250 ton crawler)
2-Sennebogen 5500 (180 ton crawler)
3- Grove GMK 6220 (220 ton mobil)
4-Grove GMK 6200 (225 ton mobil)
5-Liebherr LTM 1120 (120 ton mobil)
6-Liebherr LTM 1100 (100 ton mobil)
7-Liebherr LTM 1070 (80 ton mobil)
8-Liebherr LTM 1070-1 (80 ton mobil)
9-Grove GMK 3055 (60 ton mobil)
10-Liebherr LTM 1045-1 (50 ton mobil)
11-Liebherr LTM 1045 (50 ton mobil)
12-Demag KF 30 (30 ton mobil)
13-Hi-UP (40 ton mobil)
14-Hi-UP (35 ton mobil)
15-Hi-UP (30 ton mobil)
16-JLG Manlift (35 m height acess)
16 cranes from our fleet have been operating during
the one of the biggest investments of Iron-Steel
factory construction by İCDAS Çelik Enerji Tersane
ve Ulaşım Sanayii A.Ş, in Çanakkale Biga.
The project has started at the beginning of 2007 and
it is still going on. IZMIR VINC has been serving on
the site with 1 engineer, 1 formen, 18 operators,
technicians, mechanics. The project is scheduled to
be finalised at the last quarter of 2008.
|